Tentative Time
Frame:
March: bid construction
Mid-Late April: Renovations
begin
August 15th: Move in
House Configuration:
First Floor: Formal foyer and front room, Dining room, kitchen, living room
and handicapped accessible full bath. Front porch and back deck.
Second Floor: 3 single and 2 double bedrooms. Bath with 2 showers.
Basement: Laundry and Heating/Utility Room.
Financing:
All costs for the change of use from a single family rental to a fraternity
house will be the responsibility of the fraternity.
Ownership:
The property is and will continue to be owned by the University
Partial List
of Upgrades and Renovations:
Full Tech upgrade to University ethernet, phone, and cable
Fire Code upgrades: Sprinklers, fire alarm and notificaiton systems, sealed
utility room,
render fireplace inoperable.
Handicapped Related: Addition of HC accessible bath on first floor, wheelchair
ramp to
back door, slight kitchen modifications, doorway and hallway widenings on
first floor
Parking: Addition of handicapped and regular parking spaces on sides of house.
Other: Seal off attic, General fix-it items, new doors, Demolition of existing
first floor bathroom
Addition of letters on side and front of house